Guelph road work from November 30: Borden Street closed to through traffic, a Cassino Avenue lane shut, and speed tables going in near three schools

Water service work closes Borden Street to through traffic between University Avenue West and Dean Avenue and shuts a westbound lane on Cassino Avenue from about November 30, while speed table work continues on eight streets until December 18.

The update

  • From on or about Monday, November 30, Borden Street is closed to through traffic from University Avenue West to Dean Avenue for about two weeks; local traffic is allowed.
  • The same day, the westbound lane of Cassino Avenue closes at 58 Cassino Avenue, the north sidewalk closes from William Street to Victoria Road North, and route 13 buses may be delayed.
  • Speed tables are being built near Westminster Woods, Sacred Heart and Victory schools, with lane reductions on eight streets until December 18.

Why it matters. Drivers, bus riders and pedestrians using Borden Street, Cassino Avenue and eight streets near three schools face closures, lane reductions and delays into mid-December.

Borden Street: closed to through traffic

Borden Street will be closed to through traffic from University Avenue West to Dean Avenue starting on or about Monday, November 30, the City of Guelph said in a construction notice dated November 26. The work is expected to take about two weeks, weather permitting. Local traffic will still be allowed on Borden Street, but there will be no through access from 10 Borden Street to the University Avenue West intersection.

The contractor, McGillivray Trenchless, is removing road asphalt, curb and boulevard to install a new water service for an additional dwelling unit at 17 University Avenue West. The City says all surfaces will be restored to their original condition. Sidewalks, Guelph Transit and waste collection are not affected. The notice does not describe a signed detour.

Cassino Avenue: one lane and the north sidewalk

Also from on or about November 30, for about two weeks, the westbound lane of Cassino Avenue will be closed to through traffic at 58 Cassino Avenue while Ace Canada Construction installs a new water service for an additional dwelling unit at that address. Traffic will still be permitted on Cassino Avenue, but the City says delays are expected.

The north sidewalk on Cassino Avenue will be closed from William Street to Victoria Road North, and pedestrians are asked to use the sidewalk on the south side. The City says delays are expected on Guelph Transit route 13 because of the lane reduction. Waste collection is not affected.

The two water service jobs, as the City's November 26 notices state them
Borden Street
Closed to through traffic, University Avenue West to Dean Avenue; local traffic allowed
Cassino Avenue
Westbound lane closed at 58 Cassino Avenue; north sidewalk closed, William Street to Victoria Road North
Start
On or about Monday, November 30, 2026
Length
About two weeks each, weather permitting
Transit
Borden: no changes. Cassino: delays expected on route 13
Driveways
Access maintained where possible during working hours (7 a.m. to 7 p.m.)

Speed tables near three schools until December 18

In a separate notice dated November 23, the City said it began building speed tables on or around November 24 and expects all work to be finished by December 18, weather permitting. The traffic calming is meant to improve road safety around Westminster Woods Public School, Sacred Heart Catholic School and Victory Public School, under the City's Traffic Calming Policy and Vision Zero goals. Two-way traffic will be maintained on every street, and sidewalks, transit and waste collection are not affected, though construction may temporarily affect access to private property.

  • Alice Street, from Arthur Street South to Stevenson Street South
  • Huron Street, from Elizabeth Street to Alice Street
  • Goodwin Drive, from Beaver Meadow Drive to Dominion Drive
  • Hall Avenue, from Goodwin Drive to Dominion Drive
  • Tolton Drive, from Goodwin Drive to Clair Road East
  • Exhibition Street, from Division Street to Cavell Avenue
  • Clarke Street West, from Woolwich Street to Exhibition Street
  • Powell Street West, from Woolwich Street to Exhibition Street

The dates

Borden Street and Cassino Avenue water service work begins
On or about November 30, for about two weeks, weather permitting · Milestone
Speed table work expected to be complete
Alice, Huron, Goodwin, Hall, Tolton, Exhibition, Clarke Street West and Powell Street West · Milestone

Dates as this story states them, each traced to its sources.

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.

Places in this story

The records this story is about

Streets in this story

The streets the records in this story are on. All streets