Major road projects in Guelph

The multi-year road, bridge and highway projects in Guelph that have an official project source: what is being built, where, and the timeline each source gave on the day this page was checked.

Summary

The City is rebuilding Wyndham Street downtown, with road work planned until the third quarter of 2028 and Macdonell Street next, replacing the Speed River bridge on Speedvale Avenue East by spring 2028 and rebuilding York Road east of Victoria Road to 2030. The Province lists a new Hanlon interchange from Maltby Road to the Speed River and a Highway 7 interchange near Woodlawn Road as planned, with no dates. Each timeline is as stated on November 27, 2026.

Last verified

Administered by The City of Guelph's Engineering and Transportation Services builds City road projects; the Ontario Ministry of Transportation plans and builds work on the Hanlon (Highway 6) and Highway 7. Every answer below was checked against its source on November 27, 2026; the source is linked under each one.


Downtown

What is the Downtown Infrastructure Renewal Program?

It is the City's multi-phase rebuild of downtown roads, sewers and watermains, with better sidewalks, cycling facilities and streetscape, north of the rail tracks plus Wyndham Street South and parts of Wellington Street. Phase 1 rebuilds Wyndham Street from Wellington Street East to Woolwich Street, including St. George's Square: the City's timeline shows utility relocations from the third quarter of 2025 to the third quarter of 2026 and road reconstruction from the second quarter of 2026 to the third quarter of 2028, with an approved budget of $42,465,740. Phase 2, the Macdonell Street corridor from Norfolk Street to Elizabeth Street, is in design until early 2028.

Phase 0: Wellington water and wastewater capacity
Completed in the third quarter of 2025 ($3,381,971)
Phase 1: Wyndham Street, Wellington to Woolwich
Road reconstruction Q2 2026 to Q3 2028 ($42,465,740)
Phase 2: Macdonell Street, Norfolk to Elizabeth
Design Q2 2026 to Q1 2028; construction 2028 to 2030 ($6,192,140 approved)

The City's timeline shows Phase 2 construction from 2028 to 2030, while its project details give a Phase 2 target completion of the fourth quarter of 2031.

Source: City of Guelph, Downtown Infrastructure Renewal Program

How far along is the Wyndham Street rebuild?

Construction began in April 2026. The City reports Wyndham Street from Wellington Street to Carden Street complete except minor work at the rail bridge, the Carden Street and Macdonell Street intersections reopened (Macdonell and Wyndham by August 16, 2026), and electrical utility relocation complete from Carden Street to Woolwich Street. It expects Wyndham Street to reopen for the winter by December 18, 2026, on a temporary asphalt road with temporary on-street parking, until construction resumes in spring 2027. All underground sewers and watermains are being replaced and St. George's Square rebuilt to the final plan Council approved on December 16, 2025.

Weekly updates and detour maps are on the City's Diggable Downlow project page. The Downtown Construction Office at 42 Wyndham Street North, Suite 202, has open hours Tuesdays 10 a.m. to 12 p.m. and Thursdays 1 to 3 p.m.

Source: City of Guelph, Phase 1: Wyndham Street Reconstruction


City road and bridge projects

What is happening on Speedvale Avenue?

The City is improving the whole Speedvale Avenue corridor from Elmira Road North to Stevenson Street over several years. On Speedvale Avenue East, Phase 1 (Glenwood Avenue to east of the Guelph Junction Railway tracks, widened to two lanes each way) is complete; Phase 2, which started in February 2026, replaces the Speed River bridge with a four-lane bridge with multi-use paths both ways and a trail connection underneath, and is expected to finish by spring 2028; Phase 3, Riverview Drive to Manhattan Court, is scheduled to start in 2028 after an open house in 2027.

Phase 1: Glenwood Avenue to east of the GJR tracks
Complete
Phase 2: Speed River bridge replacement
Construction 2026 to 2028
Phase 3: Riverview Drive to Manhattan Court
Planned start 2028

On Speedvale Avenue West, the City plans to replace the watermain between Silvercreek Parkway North and Lewis Road in 2029.

Source: City of Guelph, Speedvale Avenue East Improvements

When will the York Road reconstruction be finished?

The City expects all construction on York Road to be complete by 2030. Phases 1 to 3, Wyndham Street to Victoria Road South, were done in 2017, 2022 and spring 2025. Phase 4, Victoria Road South to the east city limit, began in spring 2025 and runs in stages: Stage 1, Watson Parkway to the east city limit, is underway; Stage 2, Victoria Road South to Industrial Street and the north side of Watson Road, is planned for 2027; and Stage 3, Industrial Street to Watson Parkway, for 2028. The work adds new watermains and sewers, a multi-use path, stormwater infiltration basins and new signals at Watson Parkway and Watson Road.

The City says two-way traffic is kept on York Road throughout, with no full closures planned, and that these dates are estimates that may change.

Source: City of Guelph, York Road Reconstruction

What is being done on University Avenue West?

Between College Avenue West and Gordon Street, the City is replacing the sanitary and storm sewers, upsizing the watermain and improving sidewalks and drainage, including a new sidewalk from College Avenue to Caledonia Street. Its timeline shows construction starting in June 2026, pausing in December 2026, resuming in spring 2027 and ending in fall 2027.

The City's November 26, 2026 notice expects a full closure from just east of Talbot Street to Gordon Street from April to December 2027, with local access only.

Source: City of Guelph, University Avenue West Improvements

Which City road projects are still in design?

Edinburgh Road South between Wellington Street West and Manor Park Crescent, including structural repairs to the Edinburgh Road bridge over the Speed River, new multi-use paths and a better Wellington Street West intersection, is in detailed design for 2026 and 2027, with an open house in winter 2027 and construction in 2027 and 2028. Gordon Street between Edinburgh Road and Lowes Road, studied in an environmental assessment, is in detailed design with a new storm sewer, and the City estimates construction will begin in 2026 or 2027.

Source: City of Guelph, Edinburgh Road Bridge Repairs and Edinburgh Road Improvements


Provincial highway projects

What is planned for the Hanlon Expressway in Guelph?

The Province's 2026 Southern Highways Program lists the reconstruction of Highway 6 from Maltby Road to the Speed River, with a new interchange, as an upcoming expansion project: 11.4 km, estimated at $500 million to $1 billion, with planning and environmental assessment underway and no start or completion date. The City's summary of the design study says the plan is to make that section a controlled-access freeway, with a partial interchange at Kortright Road and Downey Road, a full interchange at Stone Road and a bridge carrying College Avenue over the highway with no connection to it.

The City says construction will be scheduled after design, property acquisition, utility relocation, environmental approvals and funding. The provincial program also lists rehabilitation of the Hanlon Creek culvert and Speed River bridges and of the Speedvale Creek culvert for 2028 to 2029, with design upcoming.

Source: Government of Ontario, 2026-2029 Southern Highways Program (summer 2026)

Where is the new Highway 7 between Kitchener and Guelph?

The Province's 2026 program lists Highway 7 from Kitchener to Guelph, Phase 3, as a new four-lane highway with a new bridge, 18.4 km and over $1 billion, with planning and environmental assessment underway and no dates. It also lists a new interchange on Highway 7 from just north of Speedvale Avenue to north of Woodlawn Road in Guelph, estimated at $25 million to $50 million, with design underway. The City says the new freeway will connect Highway 85 in Kitchener with the Hanlon in Guelph, including a new interchange at Woodlawn Road and Silvercreek Parkway.

Neither source gives a construction start for the Guelph sections.

Source: Government of Ontario, 2026-2029 Southern Highways Program (summer 2026)

Sources

Every factual claim above traces to one of these documents.

  1. City of Guelph

    Downtown Infrastructure Renewal Program

    Retrieved November 27, 2026

  2. City of Guelph

    Phase 1: Wyndham Street Reconstruction

    Retrieved November 27, 2026

  3. City of Guelph

    Speedvale Avenue East Improvements

    Retrieved November 27, 2026

  4. City of Guelph

    York Road Reconstruction

    Retrieved November 27, 2026

  5. City of Guelph

    University Avenue West Improvements

    Retrieved November 27, 2026

  6. City of Guelph

    Edinburgh Road Bridge Repairs and Edinburgh Road Improvements

    Retrieved November 27, 2026

  7. Government of Ontario

    2026-2029 Southern Highways Program (summer 2026)

    Published August 7, 2026 · Retrieved November 27, 2026