Why is there not two-way, all-day GO train service to Guelph?
Metrolinx says it primarily runs on a single track on much of the Kitchener line between Bramalea GO and Kitchener GO, shared with CN freight, which limits how often two-way trains can run. In October 2025 it announced an agreement in principle to buy part of the 26.2 km of CN track between Bramalea and Georgetown GO stations, and plans more than 40 km of new track; once that multi-year work is done, it says it can provide two-way, all-day hourly service to Kitchener and Guelph, seven days a week.
Metrolinx says construction begins once designs are finalized and gives no date for the new service. Check GO Transit's schedules for today's trips from Guelph Central GO.
Source: Metrolinx, Metrolinx closer to two-way all-day service on Kitchener Line
Have any Kitchener line trips been added recently?
Metrolinx said that from April 27, 2026 it added two weekday counter-peak express trains between Kitchener and Union Station: an eastbound afternoon trip leaving Kitchener at 15:43 and arriving at 17:17, and a westbound morning trip leaving Union Station at 08:49 and arriving in Kitchener at 10:26. It also said many trains across the network would change length, so riders may need to wait at a different spot on the platform.
Metrolinx's notice does not say whether these express trips stop at Guelph Central GO; check the schedule.
Source: Metrolinx, Additional GO train service coming to Kitchener Line
What track and platform work is happening at Guelph Central?
The City says Metrolinx is building a platform on the south side of Guelph Central Station, from just west of Wyndham Street east to about where Neeve Street would cross the tracks, and is re-installing a second track between Silvercreek Parkway and the station; the final phase of the track work needs short-term road closures on Alma Street, Edinburgh Road, Yorkshire Street and Glasgow Street. GO Transit's station notice says door restrictions are in place for 12-coach trains during the platform work.
The City also lists a study of electrifying the rail line from Georgetown to Kitchener, which it says is paused.
Source: City of Guelph, Metrolinx in Guelph
What else is planned for the Kitchener line around Guelph?
In May 2024 Metrolinx said a second platform at Guelph Central GO, a 2.6 km passing track in Breslau and a new maintenance-vehicle storage track west of Guelph were complete. It listed the next package of work as including a passing track at Acton GO, a north platform extension at Guelph GO, a passing track at Guelph GO, an extended second track in Breslau, track upgrades in Kitchener and new train storage between Mount Pleasant and Georgetown stations, which together let trains pass each other between Georgetown and Kitchener.
That article said the package was expected to go to bid in 2024; Metrolinx has not posted completion dates for these pieces.
Source: Metrolinx, Key progress update for Kitchener GO Line
Where does the GO rail line cross Guelph streets at grade?
The City lists six at-grade rail crossings on the Kitchener GO line in Guelph: Alma Street, Edinburgh Road, Yorkshire Street, Glasgow Street, Dublin Street (now closed) and Watson Road North. The City is studying, with Parsons Inc., whether the Edinburgh Road crossing needs grade separation and how people walking, cycling and driving cross the corridor, including possible new walking and cycling crossings at Margaret Greene Park, Dublin Street and Cityview Drive.
Source: City of Guelph, Metrolinx in Guelph